Power plant and electricity economics
Before we look at construction costs, it’s useful to have some context about the economics of electricity production.
We can roughly break the costs of operating a power plant into three categories – fuel costs, operation and maintenance costs, and capital costs (the amortized cost from building the plant.) Different types of power plants have different cost fractions. For natural gas plants, for instance, up to 70% of the cost of their electricity will be from fuel costs (depending on the price of gas.) With nuclear power, on the other hand, a large fraction (60-80%) of the cost of their electricity comes from capital costs – the costs of building the plant itself. Nuclear plant construction costs thus have a large impact on the cost of their electricity.
Because nuclear plants are expensive, and they take a long time to build, financing their construction can also be a significant fraction of their cost, typically around 15-20% of the cost of the plant. For plants that have severe construction delays and/or have high financing costs (such as the Vogtle 3 and 4 plants in Georgia), this can be 50% of the cost or more.
(Comparison between different types of power plants is often done using “overnight costs”, or the cost to build them if they were built overnight and didn’t have to pay interest charges. Because nuclear plants reliably take longer (sometimes much longer) to build than other types of power plants, this biases comparisons in favor of nuclear plants.)
The cost fractions (as well as technological capabilities) of different types of power plants impact how they get used. Because electricity can’t be cheaply stored, at any given moment the amount of electricity produced has to balance with the amount consumed. Since electricity consumption varies over time, power plants are brought on and offline as demand changes (this is called “dispatch”.) The order plants are dispatched is generally a function of their variable costs of production (with lower cost plants coming on first), as well as how easy it is for them to ramp their production up or down.
Because the cost of nuclear power electricity is largely due to capital costs (that you would be paying for whether the plants produced electricity or not), and because plants in the US have often not been designed to ramp up and down easily, they tend to be operated continuously. Nuclear is sometimes praised for having lower fuel costs, but all else being equal (ie: assuming total production cost stays constant), it’s better to have a larger fraction of your electricity costs be variable, so that if demand drops then production cost drops as well.
(This is another complicating factor in comparing different types of power plants. Comparison is often done by comparing a plant’s “levelized cost of electricity” (LCOE), which is the net present cost of the electricity a plant will produce over its lifetime. But the value of the electricity a plant produces is different at different times. For instance, half the time a nuclear plant will be operating at night, when the price of electricity might be lower (depending on the utility provider.) By contrast, natural gas peaker plants will be used when demand is unexpectedly high, and the price of electricity is much higher. Intermittent sources such as wind and solar will sometimes produce more electricity than is expected or needed, which can push down the price, in some cases enough that the price actually goes negative. Nuclear, wind, and (sometimes) solar thus might often be selling less valuable electricity than other types of power plants.)
Nuclear power basics
It’s also useful to have a bit of context about how a nuclear plant works. A nuclear power plant is a type of thermal power plant, where a heat source is used to turn water into steam, which then drives a turbine. For nuclear power, the heat source is radioactive nuclear fuel producing a nuclear chain reaction.
Nearly all nuclear reactors in the US (and around the world) are light water reactors (LWR), where the reactor heats a supply of light water (normal H2O), which then transfers its heat to a second source of water, which then drives the turbine (this keeps the irradiated water separated from the rest of the plant.) In a light water reactor, water is also used as the neutron moderator, the material that slows down emitted neutrons so they trigger more fission events.
(Diagram of a pressurized water reactor, via the Department of Energy. The other major type of LWR is a boiling water reactor (BWR), where steam is created in the pressure vessel directly.)
A major risk for this type of reactor is a “loss of cooling accident” (LOCA). If a pipe bursts, or the supply of cooling water is otherwise disrupted and isn’t available to cool the nuclear fuel, the fuel can heat up to the point where it melts (a “core meltdown”), potentially damaging the reactor and exposing radioactive material. (This type of failure led to the phrase “China Syndrome”, the idea that in a nuclear meltdown the molten fuel would burn its way through the reactor housing, then the containment, then into the surface of the earth and (figuratively) make its way to China.) Both the Fukushima and Chernobyl power plants experienced core meltdowns, and Three Mile Island experienced a partial core meltdown (that largely remained contained inside the reactor.)
Even after the reactor is turned off, the radioactive materials in the reactor continue to generate heat for an extended period of time (this is known as “decay heat”). Thus even in a disaster that causes the reactor to be shut down, cooling systems are still needed to keep the nuclear fuel cool. This means that cooling systems must be able to handle a wide variety of potential failure modes and environmental conditions – regardless of what happens to the reactor or the plant, the cooling systems must keep working. (As we’ll see, one way of thinking about the steady increase in nuclear plant regulations is that they’re the result of constantly learning new things that can happen to a reactor.)
Nuclear power costs
The US seems to do especially badly here, but most other countries have seen steadily rising costs. Here’s French costs (which some experts suggest is an underestimate):
And here’s German and Japanese costs:
The only country where the costs of nuclear plant construction seem to have steadily decreased is South Korea:
Because plants take so long to build, these cost increases tended to be seen on in-progress plants – a 1982 analysis found that the final construction cost for US plants ended up being anywhere from 2 to 4 times as high as the initial estimated cost:
What does that money get spent on when building a plant?
Roughly 1/3rd of the costs are “indirect costs” – engineering services, construction management, administrative overhead, etc. For the direct costs, the reactor, the turbine equipment, and the plant structures each make up a similar fraction, with the balance made up by additional plant systems. Also note that the engineering design for the plant costs nearly as much as the reactor itself.
One thing that this makes clear is that nuclear plants are very labor intensive to build (with probably at least 50% of the cost from indirect costs and on-site labor), which suggests that construction cost comparisons between countries probably need to be wage-adjusted to be relevant (for some reason it seems like most comparisons don’t do this.)
Rising labor costs
So costs, especially in the US, increased dramatically over a relatively short period of time. Nuclear plant construction is often characterized as exhibiting “negative learning” – instead of getting better at building the plants over time, we’re getting worse (in terms of cost to build them, at least.) What do we know about why costs increased?
Other estimates seem roughly in line with this. A 1980 estimate produced by Oak Ridge suggests that material volume increases between the early 1970s and 1980 generally ranged from 25-50% (not nearly enough to account for the cost increases seen):
Regulation increase and project disruption
Why did labor costs increase? The typical story here is one of increasing regulation making the plants increasingly burdensome to build. During the late 60s and early 70s, nuclear requirements steadily increased:
As did the thoroughness of review by the Nuclear Regulatory Commission (the Federal organization responsible for issuing plant operating licenses):
And the previous Eash-Gates study found that at least 30% of the cost increase between 1976 and 1988 can be attributed to increased regulation (and probably much more.)
An overview of the impact of increased regulation is given by Charles Komonoff in his 1981 “Power Plant Cost Escalation”:
One key indicator of regulatory standards, the number of Atomic Energy Commission (AEC) and Nuclear Regulatory Commission (NRC) “regulatory guides” stipulating acceptable design and construction practices for reactor systems and equipment, grew almost seven-fold, from 21 at the end of 1971 to 143 at the end of 1978. Professional engineering societies developed new nuclear standards at an even faster rate (often in anticipation of AEC/NRC. These led to more stringent (and costly) manufacturing, testing, and performance criteria for structural materials such as concrete and steel, and for basic components such as valves, pumps, and cables.
Requirements such as these had a profound effect on nuclear plants during the 1970s. Major structures were strengthened and pipe restraints added to absorb seismic shocks and other postulated “loads” identified in accident analyses. Barriers were installed and distances increased to prevent fires, flooding, and other “common-mode” accidents from incapacitating both primary and back-up groups of vital equipment. Similar measures were taken to shield equipment from high-speed missile fragments that might be loosed from rotating machinery or from the pressure and fluid effects of possible pipe ruptures. Instrumentation, control, and power systems were expanded to monitor more plant factors under a broadened range of operating situations and to improve the reliability of safety systems. Components deemed important to safety were “qualified” to perform under more demanding conditions, requiring more rigorous fabrication, testing, and documentation of their manufacturing history.
Over the course of the 1970s, these changes approximately doubled the amounts of materials, equipment, and labor and tripled the design engineering effort required per unit of nuclear capacity, according to the Atomic Industrial Forum.
These increases often had an especially large impact because they required changes to in-progress nuclear plants:
…because many changes were mandated during construction as new information relevant to safety emerged- much construction lacked a fixed scope and had to be let under cost-plus contracts that undercut efforts to economize. Completed work was sometimes modified or removed, often with a “ripple effect” on related systems. Construction sequences were frequently altered and schedules for equipment delivery were upset, contributing to poor labor productivity and hampering management efforts to improve construction efficiency. In general. reactors in the 1970s were built increasingly in an ”environment of constant change” that precluded control or even estimation of costs and which magnified the direct cost impacts of new regulations and design changes.
This environment of constant change helps explain the huge increase in labor costs – changing an in-progress plant will add costs and slow down construction, even if the design changes don’t result in substantially more material or equipment use.
(This will continue next week with Part II. Thanks to Titus Reed and Austin Vernon for reading drafts of this)
Related posts
Tips & Trick For Healthy Glowing Skin
Send to HN Lorem ipsum dolor sit amet, consectetur adipiscing elit. Nam laoreet, nunc et accumsan cursus, neque eros sodales…
My Fight With Depression. Concussions
Send to HN Lorem ipsum dolor sit amet, consectetur adipiscing elit. Nam laoreet, nunc et accumsan cursus, neque eros sodales…
How I Traveled The World With Only $100
Send to HN Lorem ipsum dolor sit amet, consectetur adipiscing elit. Nam laoreet, nunc et accumsan cursus, neque eros sodales…
What’re People Buzzing About? Your Content Should Join The Conversation
Send to HN Sed faucibus ultrices orci ac malesuada. Cras eu ante dapibus, imperdiet lacus ac, pulvinar nulla. Interdum et…
Does Coffee Help Deduce Stress Hormone Levels?
Send to HN Lorem ipsum dolor sit amet, consectetur adipiscing elit. Nam laoreet, nunc et accumsan cursus, neque eros sodales…
Review Of Healthy Breakfast Meals For Energy Boost
Send to HN Lorem ipsum dolor sit amet, consectetur adipiscing elit. Quisque hendrerit fringilla enim, ut scelerisque dui. In hac…
How Much Time On Social Networks Is Considered Healthy
Send to HN Lorem ipsum dolor sit amet, consectetur adipiscing elit. Nam laoreet, nunc et accumsan cursus, neque eros sodales…
My Fight With Depression. Concussions
Send to HN Lorem ipsum dolor sit amet, consectetur adipiscing elit. Nam laoreet, nunc et accumsan cursus, neque eros sodales…